Dulater Hill Wind Farm (57.8 MW)
Dulater Hill Wind Farm is a 57.8 MW wind farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 24 May 2019; the record was last updated on 25 June 2019. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.
Planning timeline
| Date | Stage |
|---|---|
| 30 June 2014 | Application submitted |
| 4 March 2016 | Appeal lodged |
| 24 May 2019 | Refused by the planning authority |
| 24 May 2019 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 57.8 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 25 June 2019
- Operator or applicant
- Ecotricity
- Planning authority
- Scottish Government (S36)
- Planning application reference
- not recorded
- Appeal reference
- WIN-340-2
- Turbines
- 17
- Turbine height
- 125 m
- Address (REPD)
- North of the A923, near Butterstone
- Council area (by location)
- Perth and Kinross
- Time to decision
- 256 weeks
- REPD reference
- 4274
Who decides
As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.617, -3.4855).