Binn Eco Park Solar (5 MW)

Binn Eco Park Solar is a 5 MW solar farm project in Perth and Kinross, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 September 2021, not yet built; the record was last updated on 23 February 2024. REPD also records that the planning permission expired on 29 September 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
approved, not builtmay be out of datestatus in REPD
23 February 2024record last updated
Perth and Kinrosscouncil area

REPD also records that the planning permission expired on 29 September 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
12 May 2021Application submitted
29 September 2021Planning permission granted
29 September 2024Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
23 February 2024
Operator or applicant
Green Cat Renewables Developments
Planning authority
Perth and Kinross
Planning application reference
21/00705/FLL
Site area
9.8 ha
Address (REPD)
150 Metres Ne/O Binn Hill, Transmitting Station, Glenfarg, Perth
Council area (by location)
Perth and Kinross
Time to decision
20 weeks
Name in REPD
Binn Eco Park - Solar
REPD reference
9071

Who decides

ApplicationsPerth and KinrossUK
Decided applications (solar, wind, battery)7310,236
Refused32 (44%)19%
Solar refused6 of 2412%
Onshore wind refused23 of 3145%
Battery storage refused3 of 1816%
Median time from submission to decision28.3 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

Other large projects within 10 km

ProjectTypeMWStatuskm
Binn Eco Park Batterybattery storage10approved, not built0.1
Binn Eco Park Wind Farmwind farm10operational0.6
Binn Eco Park Wind Farmwind farm10refused0.6
Carey Solar Farmsolar farm10permission expired3.5
Newburgh Road, Abernethybattery storage49.9approved, not built4.4
Cordon Farm, Abernethybattery storage30application submitted4.5
Cordon Farmsolar farm10permission expired4.7
Jamesfield Garden Centre, Newburghbattery storage49.9application submitted4.8
Newburgh Road, Abernethybattery storage15approved, not built5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3048, -3.3392).