Westfield (10 MW wind farm)

Westfield is a 10 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2013; the record was last updated on 4 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
operationalstatus in REPD
4 June 2013record last updated
Fifecouncil area

Planning timeline

DateStage
31 July 2009Application submitted
22 June 2012Planning permission granted
30 July 2012Construction started
31 March 2013Operational

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
4 June 2013
Operator or applicant
Ventient (formerly Infinis)
Planning authority
Fife
Planning application reference
09/01861/EIA
Turbines
4
Address (REPD)
Near Kingassie, Lochgelly, Fife. KY5 0J
Council area (by location)
Fife
Time to decision
151 weeks
REPD reference
3684

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Former Fife Power Stationbattery storage100application submitted2.1
Strathruddie, Kinglassie Solar farmsolar farm25approved, not built3.1
Westfield Solar Farm & Batterysolar farm30approved, not built3.7
Glenniston Farm, Auchtertool Solar Farmsolar farm39approved, not built3.9
Little Raith Farm - extensionwind farm18refused on appeal3.9
Little Raith Farmwind farm25operational3.9
Clentrie Wind Farm (Gevens)wind farm6.9operational4.0
Gleniston, Auchtertoolbattery storage49.5approved, not built4.1
Camilla Battery Storagebattery storage50operational4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.1453, -3.2949).