Craigannet Wind Farm (15 MW)

Craigannet Wind Farm is a 15 MW wind farm project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 21 November 2012; the record was last updated on 1 May 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
refused on appealstatus in REPD
1 May 2013record last updated
Stirlingcouncil area

Planning timeline

DateStage
2 February 2012Application submitted
31 August 2012Refused by the planning authority
21 November 2012Appeal refused

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
refused on appeal
Record last updated
1 May 2013
Operator or applicant
Lomond Energy
Planning authority
Stirling
Planning application reference
12/00056/FUL
Appeal reference
PPA-390-2022
Turbines
6
Address (REPD)
885 Metres Nw/O Craigannet Farm, Fintry, Glasgow, Strathclyde, G33
Council area (by location)
Stirling
Time to decision
30 weeks
Name in REPD
CRAIGANNET WIND FARM
REPD reference
3907

Who decides

ApplicationsStirlingUK
Decided applications (solar, wind, battery)2310,236
Refused7 (30%)19%
Solar refused0 of 712%
Onshore wind refused6 of 1145%
Battery storage refused1 of 516%
Median time from submission to decision30.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Craigengeltwind farm20operational1.9
Carron Valley (Cairnoch Hill) Wind Farmwind farm45refused on appeal2.4
Muirparkwind farm33refused3.8
Earlsburnwind farm37.5operational4.0
Glenhead Farm (Upper)solar farm5permission expired5.3
Craigton and Spittalhill Wind Farmwind farm21permission expired6.3
Rullie Community Windfarmwind farm25application withdrawn6.4
Earlsburn North (Kingsburn) Wind Farmwind farm22.5operational6.6
Earlsburn Wind Farm Extensionwind farm34approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0397, -4.0642).