Energy Projects Near You

Craigton and Spittalhill Wind Farm (21 MW)

Craigton and Spittalhill Wind Farm is a 21 MW wind farm project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 17 November 2018; the record was last updated on 18 July 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWwind farm
permission expiredstatus in REPD
18 July 2019record last updated
Stirlingcouncil area

Planning timeline

DateStage
5 December 2013Application submitted
24 March 2015Refused by the planning authority
23 June 2015Appeal lodged
17 November 2015Planning permission granted
17 November 2015Appeal allowed
17 November 2018Permission expired

Project details

Technology
wind farm
Capacity
21 MW
Status (REPD)
permission expired
Record last updated
18 July 2019
Operator or applicant
Force 9 Energy LLP and EDF Energy
Planning authority
Stirling
Planning application reference
13/00728/FUL
Appeal reference
PPA-390-2039
Turbines
7
Turbine height
125 m
Address (REPD)
Land 2 Kilometres North West Of Wester Cringate, Polmaise Road To Carron Reservoir Stirling
Council area (by location)
Stirling
Time to decision
102 weeks
REPD reference
3625

Who decides

ApplicationsStirlingUK
Decided applications (solar, wind, battery)2310,236
Refused7 (30%)19%
Solar refused0 of 712%
Onshore wind refused6 of 1145%
Battery storage refused1 of 516%
Median time from submission to decision30.1 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Earlsburn North (Kingsburn) Wind Farmwind farm22.5operational2.3
Earlsburnwind farm37.5operational3.2
Carron Valley (Cairnoch Hill) Wind Farmwind farm45refused on appeal4.2
Craigannet Wind Farmwind farm15refused on appeal6.3
Craigengeltwind farm20operational6.4
Muirparkwind farm33refused7.5
Patrickston Farmsolar farm15permission expired7.6
Ballindalloch Muirwind farm20refused8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.073, -4.1471).