Ballindalloch Muir (20 MW wind farm)
Ballindalloch Muir is a 20 MW wind farm project in Stirling, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 12 November 2009; the record was last updated on 24 November 2009.
20 MWwind farm
refusedstatus in REPD
24 November 2009record last updated
Stirlingcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 20 December 2007 | Application submitted |
| 12 November 2009 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 20 MW
- Status (REPD)
- refused
- Record last updated
- 24 November 2009
- Operator or applicant
- Npower Renewables
- Planning authority
- Stirling
- Planning application reference
- not recorded
- Turbines
- 9
- Address (REPD)
- Ballindalloch Muir, Balfron, Stirling
- Council area (by location)
- Stirling
- Time to decision
- 99 weeks
- REPD reference
- 2909
Who decides
| Applications | Stirling | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 23 | 10,236 |
| Refused | 7 (30%) | 19% |
| Solar refused | 0 of 7 | 12% |
| Onshore wind refused | 6 of 11 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 30.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Craigton and Spittalhill Wind Farm | wind farm | 21 | permission expired | 8.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.0867, -4.2879).