Greengairs Wind Farm (17.5 MW)

Greengairs Wind Farm is a 17.5 MW wind farm project in North Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired; the record was last updated on 23 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.5 MWwind farm
permission expiredstatus in REPD
23 September 2020record last updated
North Lanarkshirecouncil area

Planning timeline

DateStage
7 February 2007Application submitted
14 August 2008Planning permission granted

Project details

Technology
wind farm
Capacity
17.5 MW
Status (REPD)
permission expired
Record last updated
23 September 2020
Operator or applicant
Muirhall Energy (formerly Infinis)
Planning authority
North Lanarkshire
Planning application reference
07/00172/FUL
Turbines
9
Address (REPD)
Greengairs Landfill Site Meikle Drumgray Road Greengairs North Lanarkshire
Council area (by location)
North Lanarkshire
Time to decision
79 weeks
REPD reference
4106

Who decides

ApplicationsNorth LanarkshireUK
Decided applications (solar, wind, battery)3810,236
Refused9 (24%)19%
Solar refused0 of 1412%
Onshore wind refused8 of 2045%
Battery storage refused1 of 416%
Median time from submission to decision34.4 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Greengairs East Wind Farmwind farm24operational1.1
Nether braco Farmwind farm21application withdrawn5.6
Bracco / Black Hillwind farm72.5application withdrawn5.8
Burnbank Street, Greenhillbattery storage30approved, not built6.9
Locks Street, Coatdyke Battery Energy Storage Systemsbattery storage45application submitted7.2
Easter Drumclair Woodwind farm6approved, not built7.4
Forrestfield Wind Farmwind farm13.2application submitted7.5
North Lanrigg Energy Storagebattery storage200approved, not built8.0
Salsburghwind farm24application withdrawn8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9065, -3.9263).