Newarthill Energy Park (300 MW)

Newarthill Energy Park is a 300 MW battery storage project in North Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 February 2025, not yet built; the record was last updated on 5 August 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

300 MWbattery storage
approved, not builtstatus in REPD
5 August 2025record last updated
North Lanarkshirecouncil area

Planning timeline

DateStage
9 November 2023Application submitted
4 February 2025Section 36 consent granted (Scottish Ministers)

Project details

Technology
battery storage (stand-alone storage)
Capacity
300 MW
Status (REPD)
approved, not built
Record last updated
5 August 2025
Operator or applicant
Geocore Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004953
Address (REPD)
Legbrannock Road, Newarthill
Council area (by location)
North Lanarkshire
Time to decision
65 weeks
REPD reference
14763

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Biggar Road, Clelandbattery storage30approved, not built0.6
North Lanrigg Energy Storagebattery storage200approved, not built1.9
Fernishaw Solar Farm & Battery Energy Storage Facilitysolar farm75approved, not built4.2
Salsburghwind farm24application withdrawn4.2
Hartwoodwind farm30application withdrawn5.2
Locks Street, Coatdyke Battery Energy Storage Systemsbattery storage45application submitted5.4
Wishaw Battery Storage Facilitybattery storage50operational6.3
Hartwood Windfarmwind farm21permission expired6.6
Burnbank Street, Greenhillbattery storage30approved, not built6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8254, -3.9431).