Rogerhill Solar and Battery Energy Storage System (100 MW)

Rogerhill Solar and Battery Energy Storage System is a 100 MW solar farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 15 January 2025, no decision recorded; the record was last updated on 31 January 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWsolar farm
application submittedstatus in REPD
31 January 2025record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
15 January 2025Application submitted

Project details

Technology
solar farm
Capacity
100 MW
Status (REPD)
application submitted
Record last updated
31 January 2025
Operator or applicant
Green Switch Capital Limited
Planning authority
Scottish Government (S36)
Planning application reference
P/25/0018
Site area
207.0 ha
Address (REPD)
Land 300M West Of Rogerhill Farm Rogerhill Farm Vere Road Kirkmuirhill
Council area (by location)
South Lanarkshire
REPD reference
14193

The scheme also includes 100 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Lochhead Farmwind farm6operational5.7
Auchrobert Wind Farmwind farm36operational6.5
Shaws Farmbattery storage5permission expired7.1
Coalburn Energybattery storage500under construction7.1
Nutberry Wind Farmwind farm15operational7.3
Cartland Muir Wind Farmwind farm5refused7.3
Cumberhead West Wind Farmwind farm126under construction7.4
Carlisle Roadbattery storage200approved, not built8.1
Coalburn II Energy Storage Facilitybattery storage1,000under construction8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6644, -3.9097).