Cartland Muir Wind Farm (5 MW)

Cartland Muir Wind Farm is a 5 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 1 December 2011; the record was last updated on 7 December 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWwind farm
refusedstatus in REPD
7 December 2011record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
21 June 2011Application submitted
1 December 2011Refused by the planning authority

Project details

Technology
wind farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
7 December 2011
Operator or applicant
Energy4All
Planning authority
South Lanarkshire
Planning application reference
CL/11/0266
Turbines
2
Address (REPD)
3km South West of Carluke town Centre, South Lanarkshire
Council area (by location)
South Lanarkshire
Time to decision
23 weeks
REPD reference
2771

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill Rig Community Wind Farmwind farm28refused4.2
Rogerhill Solar and Battery Energy Storage Systemsolar farm100application submitted7.3
Black Law Extension - 1awind farm48.4operational7.7
Black Law Extension - 1bwind farm15operational7.7
Black Lawwind farm124operational7.7
Watsonhead Wind Farmwind farm8.4operational8.8
Shaws Farmbattery storage5permission expired9.5
Coalburn II Energy Storage Facilitybattery storage1,000under construction9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6978, -3.8092).