Cumberhead West Wind Farm (126 MW)

Cumberhead West Wind Farm is a 126 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 October 2023; the record was last updated on 1 November 2023. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

126 MWwind farm
under constructionstatus in REPD
1 November 2023record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
2 December 2020Application submitted
18 November 2021Section 36 consent granted (Scottish Ministers)
1 October 2023Construction started

Project details

Technology
wind farm
Capacity
126 MW
Status (REPD)
under construction
Record last updated
1 November 2023
Operator or applicant
3R Energy Solutions Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00002171
Turbines
21
Turbine height
200 m
Address (REPD)
Cumberhead Forest
Council area (by location)
South Lanarkshire
Time to decision
50 weeks
Contracts for Difference
AR4
REPD reference
3328

The scheme also includes 40 MW of battery storage, recorded separately in REPD (under construction).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Carlisle Roadbattery storage200approved, not built0.7
Douglas West and Dalquhandy Renewable Energy Projectwind farm45operational1.3
Douglas West Wind Farm (extension)wind farm78under construction1.3
Nutberry Wind Farmwind farm15operational2.1
Coalburn Energybattery storage500under construction2.8
Central Eco Park Solar Farmsolar farm12approved, not built3.0
High Netherfauld House Farm 1, Tower Roadbattery storage502application submitted3.2
Poniel Wind Turbineswind farm9application withdrawn3.5
Hagshaw Hill Wind Farm Extensionwind farm26operational4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.599, -3.8875).