Douglas West Wind Farm (extension) (78 MW)

Douglas West Wind Farm (extension) is a 78 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 June 2024; the record was last updated on 2 March 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

78 MWwind farm
under constructionstatus in REPD
2 March 2026record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
12 April 2019Application submitted
18 November 2021Section 36 consent granted (Scottish Ministers)
1 June 2024Construction started

Project details

Technology
wind farm
Capacity
78 MW
Status (REPD)
under construction
Record last updated
2 March 2026
Operator or applicant
ScottishPower Renewables (UK) Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00001836
Turbines
13
Turbine height
200 m
Address (REPD)
Douglas West and Dalquhandy, F, Lesmahagow, Site West of Junction 11 of M7, Lanark,
Council area (by location)
South Lanarkshire
Time to decision
136 weeks
Contracts for Difference
AR4
REPD reference
6826

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Douglas West and Dalquhandy Renewable Energy Projectwind farm45operational<0.1
Carlisle Roadbattery storage200approved, not built0.6
Cumberhead West Wind Farmwind farm126under construction1.3
Nutberry Wind Farmwind farm15operational2.4
Hagshaw Hill Wind Farm Extensionwind farm26operational3.0
High Netherfauld House Farm 1, Tower Roadbattery storage502application submitted3.1
Poniel Wind Turbineswind farm9application withdrawn3.2
Hagshaw Hillbattery storage20approved, not built3.3
Hagshaw Hill (Repowering)wind farm84operational3.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5874, -3.8901).