Energy Projects Near You

Nutberry Wind Farm (15 MW)

Nutberry Wind Farm is a 15 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 September 2013; the record was last updated on 25 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
operationalstatus in REPD
25 March 2015record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
28 September 2006Application submitted
9 September 2008Refused by the planning authority
5 April 2011Planning permission granted
5 April 2011Appeal allowed
1 December 2011Construction started
30 September 2013Operational

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
25 March 2015
Operator or applicant
Renantis Falck Renewables Limited
Planning authority
South Lanarkshire
Planning application reference
CL/06/0662
Appeal reference
P/PPA/380/435
Turbines
6
Address (REPD)
Cumberhead, Lesmahagow, Lanark, Strathclyde. ML11 0HN
Council area (by location)
South Lanarkshire
Time to decision
236 weeks
REPD reference
3676

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cumberhead West Wind Farmwind farm126under construction2.1
Carlisle Roadbattery storage200approved, not built2.2
Douglas West Wind Farm (extension)wind farm78under construction2.4
Douglas West and Dalquhandy Renewable Energy Projectwind farm45operational2.4
Hagshaw Hill Wind Farm Extensionwind farm26operational3.7
Cumberhead Wind Farmwind farm48operational3.9
Coalburn Energybattery storage500under construction4.7
Auchrobert Wind Farmwind farm36operational4.8
Hagshaw Hill Wind Farmwind farm7.8operational4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5995, -3.9216).