Nutberry Wind Farm (15 MW)
Nutberry Wind Farm is a 15 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 September 2013; the record was last updated on 25 March 2015.
15 MWwind farm
operationalstatus in REPD
25 March 2015record last updated
South Lanarkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 28 September 2006 | Application submitted |
| 9 September 2008 | Refused by the planning authority |
| 5 April 2011 | Planning permission granted |
| 5 April 2011 | Appeal allowed |
| 1 December 2011 | Construction started |
| 30 September 2013 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 15 MW
- Status (REPD)
- operational
- Record last updated
- 25 March 2015
- Operator or applicant
- Renantis Falck Renewables Limited
- Planning authority
- South Lanarkshire
- Planning application reference
- CL/06/0662
- Appeal reference
- P/PPA/380/435
- Turbines
- 6
- Address (REPD)
- Cumberhead, Lesmahagow, Lanark, Strathclyde. ML11 0HN
- Council area (by location)
- South Lanarkshire
- Time to decision
- 236 weeks
- REPD reference
- 3676
Who decides
| Applications | South Lanarkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 89 | 10,236 |
| Refused | 30 (34%) | 19% |
| Solar refused | 2 of 20 | 12% |
| Onshore wind refused | 21 of 56 | 45% |
| Battery storage refused | 7 of 13 | 16% |
| Median time from submission to decision | 47.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Cumberhead West Wind Farm | wind farm | 126 | under construction | 2.1 |
| Carlisle Road | battery storage | 200 | approved, not built | 2.2 |
| Douglas West Wind Farm (extension) | wind farm | 78 | under construction | 2.4 |
| Douglas West and Dalquhandy Renewable Energy Project | wind farm | 45 | operational | 2.4 |
| Hagshaw Hill Wind Farm Extension | wind farm | 26 | operational | 3.7 |
| Cumberhead Wind Farm | wind farm | 48 | operational | 3.9 |
| Coalburn Energy | battery storage | 500 | under construction | 4.7 |
| Auchrobert Wind Farm | wind farm | 36 | operational | 4.8 |
| Hagshaw Hill Wind Farm | wind farm | 7.8 | operational | 4.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5995, -3.9216).