Cumberhead Wind Farm (48 MW)

Cumberhead Wind Farm is a 48 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 11 September 2023; the record was last updated on 5 April 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWwind farm
operationalstatus in REPD
5 April 2018record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
19 June 2015Application submitted
13 May 2021Planning permission granted
1 October 2021Construction started
11 September 2023Operational

Project details

Technology
wind farm
Capacity
48 MW
Status (REPD)
operational
Record last updated
5 April 2018
Operator or applicant
Octopus Renewables Infrastructure Trust
Planning authority
South Lanarkshire
Planning application reference
CL/15/0231
Turbines
12
Address (REPD)
Cumberhead, Lanark, Strathclyde
Council area (by location)
South Lanarkshire
Time to decision
308 weeks
REPD reference
5455

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Spireslack Windfarmwind farm59.6application withdrawn2.2
Nutberrywind farm60application withdrawn2.2
Hagshaw Hill Wind Farm Extensionwind farm26operational2.5
Hare Craig Windfarmwind farm36approved, not built3.0
Hagshaw Hill Wind Farmwind farm7.8operational3.0
Hagshaw Hill Wind Farmwind farm7.8operational3.1
Galawhistlewind farm66operational3.7
Nutberry Wind Farmwind farm15operational3.9
Douglas West Wind Farm (extension)wind farm78under construction4.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5718, -3.9589).