Carlisle Road (200 MW battery storage)

Carlisle Road is a 200 MW battery storage project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 April 2025, not yet built; the record was last updated on 13 May 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
approved, not builtstatus in REPD
13 May 2025record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
7 June 2023Application submitted
28 April 2025Section 36 consent granted (Scottish Ministers)
28 April 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
approved, not built
Record last updated
13 May 2025
Operator or applicant
Zenobe Energy
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004799
Address (REPD)
Coalburn Battery Energy Storage System, Adj Carlisle Road, B7078, Coalburn, Lanark
Council area (by location)
South Lanarkshire
Time to decision
99 weeks
Name in REPD
Carlisle Road - Battery Energy Storage System
REPD reference
9684

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Douglas West and Dalquhandy Renewable Energy Projectwind farm45operational0.6
Douglas West Wind Farm (extension)wind farm78under construction0.6
Cumberhead West Wind Farmwind farm126under construction0.7
Nutberry Wind Farmwind farm15operational2.2
High Netherfauld House Farm 1, Tower Roadbattery storage502application submitted3.1
Central Eco Park Solar Farmsolar farm12approved, not built3.2
Coalburn Energybattery storage500under construction3.2
Poniel Wind Turbineswind farm9application withdrawn3.3
Hagshaw Hill Wind Farm Extensionwind farm26operational3.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5927, -3.8895).