Poniel Wind Turbines (9 MW)

Poniel Wind Turbines is a 9 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 24 March 2020; the record was last updated on 19 August 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWwind farm
application withdrawnstatus in REPD
19 August 2022record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
1 February 2012Application submitted
24 March 2020Application withdrawn

Project details

Technology
wind farm
Capacity
9 MW
Status (REPD)
application withdrawn
Record last updated
19 August 2022
Operator or applicant
3R Energy (formerly Lantern Bidco)
Planning authority
South Lanarkshire
Planning application reference
CL/12/0043
Turbines
2
Address (REPD)
Land at Poniel South Lanarkshire
Council area (by location)
South Lanarkshire
REPD reference
3868

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
High Netherfauld House Farm 1, Tower Roadbattery storage502application submitted0.7
Central Eco Park Solar Farmsolar farm12approved, not built1.9
Broken Cross (Former Surface Mine)wind farm48operational2.9
Douglas West and Dalquhandy Renewable Energy Projectwind farm45operational3.2
Douglas West Wind Farm (extension)wind farm78under construction3.2
Coalburn Energybattery storage500under construction3.2
Hagshaw Hillbattery storage20approved, not built3.2
Hagshaw Hill (Repowering)wind farm84operational3.2
Coalburn II Energy Storage Facilitybattery storage1,000under construction3.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5824, -3.8408).