Energy Projects Near You

Hagshaw Hill (20 MW battery storage)

Hagshaw Hill is a 20 MW battery storage project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 February 2020, not yet built; the record was last updated on 12 June 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. REPD also records that the planning permission expired on 26 February 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
approved, not builtmay be out of datestatus in REPD
12 June 2025record last updated
South Lanarkshirecouncil area

REPD also records that the planning permission expired on 26 February 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
3 December 2018Application submitted
26 February 2020Section 36 consent granted (Scottish Ministers)
26 February 2025Permission expired

Project details

Technology
battery storage (co-located with re)
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
12 June 2025
Operator or applicant
Scottish Power Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00000737
Address (REPD)
Hagshaw Hill Wind Farm, Douglas, Lanark
Council area (by location)
South Lanarkshire
Time to decision
64 weeks
REPD reference
7572

Recorded together with Hagshaw Hill (Repowering) (84 MW wind farm, operational).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hagshaw Energy Cluster – Western Expansionsolar farm60application submitted0.1
Hagshaw Energy Cluster – Western Expansionwind farm130application submitted0.1
Hagshaw Energy Cluster – Western Expansionbattery storage225application submitted0.2
Hagshaw Hill Wind Farmwind farm7.8operational3.1
Hagshaw Hill Wind Farmwind farm7.8operational3.1
Poniel Wind Turbineswind farm9application withdrawn3.2
Hagshaw Hill Wind Farm Extensionwind farm26operational3.2
Douglas West and Dalquhandy Renewable Energy Projectwind farm45operational3.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5594, -3.871).