Hagshaw Hill (Repowering) (84 MW wind farm)

Hagshaw Hill (Repowering) is an 84 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2025; the record was last updated on 12 June 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

84 MWwind farm
operationalstatus in REPD
12 June 2025record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
3 December 2018Application submitted
26 February 2020Section 36 consent granted (Scottish Ministers)
1 November 2025Operational

Project details

Technology
wind farm
Capacity
84 MW
Status (REPD)
operational
Record last updated
12 June 2025
Operator or applicant
Scottish Power Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00000737
Turbines
14
Turbine height
200 m
Address (REPD)
Hagshaw Hill Wind Farm, Douglas, Lanark
Council area (by location)
South Lanarkshire
Time to decision
64 weeks
Contracts for Difference
AR4
REPD reference
7456

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hagshaw Hillbattery storage20approved, not built<0.1
Hagshaw Energy Cluster – Western Expansionsolar farm60application submitted0.1
Hagshaw Energy Cluster – Western Expansionwind farm130application submitted0.1
Hagshaw Energy Cluster – Western Expansionbattery storage225application submitted0.2
Hagshaw Hill Wind Farmwind farm7.8operational3.1
Hagshaw Hill Wind Farmwind farm7.8operational3.1
Poniel Wind Turbineswind farm9application withdrawn3.2
Hagshaw Hill Wind Farm Extensionwind farm26operational3.2
Douglas West and Dalquhandy Renewable Energy Projectwind farm45operational3.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5594, -3.871).