Alton Muirhouse Farm (6.8 MW wind farm)

Alton Muirhouse Farm is a 6.8 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 11 December 2018; the record was last updated on 18 December 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.8 MWwind farm
refused on appealstatus in REPD
18 December 2018record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
22 December 2015Application submitted
22 June 2018Refused by the planning authority
21 September 2018Appeal lodged
11 December 2018Appeal refused

Project details

Technology
wind farm
Capacity
6.8 MW
Status (REPD)
refused on appeal
Record last updated
18 December 2018
Operator or applicant
Private Developer
Planning authority
East Ayrshire
Planning application reference
15/0985/PP
Appeal reference
PPA-190-2069
Turbines
2
Turbine height
130 m
Address (REPD)
Land Turbines Alton Muirhouse, Newmilns
Council area (by location)
East Ayrshire
Time to decision
130 weeks
REPD reference
6022

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sneddon Law Community Wind Farmwind farm45under construction1.8
Cowans Lawwind farm49.9refused1.8
Whitelee Windfarm Extension phase 2wind farm109operational3.4
East Kingswellwind farm26refused5.7
Whitelee Windfarm Extension Phase 1wind farm108operational7.1
Whitelee Windfarm Extension Phase 3wind farm12refused on appeal7.1
Blair Data Centrewind farm13.8refused on appeal7.3
Whiteleewind farm322operational7.8
Kilmarnock Battery Energy Storage Systembattery storage500approved, not built8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6337, -4.3704).