Energy Projects Near You

Solar, wind and battery projects near Galston (KA4)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KA4 (East Ayrshire): 7 approved but not yet running, 3 operational. The largest live scheme is Kilmarnock Battery Energy Storage System (500 MW battery storage, approved on 7 April 2025, not yet built), 4.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
0awaiting a decision
7approved, not running
3operational

Projects within 10 km of KA4

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Alton Muirhouse Farmwind farmwind farm6.8refused on appealupdated Dec 2018Dec 2015refused Jun 2018Dec 2018East Ayrshire3.9
Kilmarnock Battery Energy Storage Systembattery storagebattery storage500approved, not builtupdated Jun 2026Sep 2023granted Apr 2025Jun 2026East Ayrshire4.7
Cowans Lawwind farmwind farm49.9refusedupdated Jun 2019Apr 2010refused Nov 2010Jun 2019East Ayrshire4.9
Sneddon Law Community Wind Farmwind farmwind farm45under constructionupdated Sep 2022Jan 2012granted Feb 2013Sep 2022East Ayrshire4.9
Kilmarnock South Substationbattery storagebattery storage300operationalupdated Mar 2026Feb 2022—Mar 2026East Ayrshire5.9
Whitelee Windfarm Extension phase 2wind farmwind farm109operationalupdated Apr 2013May 2009granted Dec 2009Apr 2013East Ayrshire6.0
Camsiscan Farm, Craigiebattery storagebattery storage350approved, not builtupdated Feb 2024Nov 2022granted Jan 2024Feb 2024South Ayrshire6.4
Inchbean Farm, Treeswoodhead Roadbattery storagebattery storage60approved, not builtupdated Jul 2025Nov 2023granted Jun 2025Jul 2025East Ayrshire7.0
Holmquarry Roadbattery storagebattery storage60.4approved, not builtupdated Oct 2025Mar 2024granted Jul 2025Oct 2025East Ayrshire7.5
East Kingswellwind farmwind farm26refusedupdated Nov 2015May 2010refused Dec 2010Nov 2015East Ayrshire9.6
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Elmbank Drive Solar Panelsrooftop solarrooftop solar—operationalupdated Dec 2021Jan 2021granted Aug 2021Dec 2021East Ayrshire7.0
Kilmarnock Academy, Elmbank Driverooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023East Ayrshire7.1
Moorfield North Industrial Park, Moorfieldrooftop solarrooftop solar—approved, not builtupdated Feb 2021Jan 2021granted Mar 2021Feb 2021East Ayrshire9.9

Distance from the average position of the KA4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar302100.2
Wind farm5011345
Battery storage50410970

MW in pipeline: pending, approved and under-construction capacity.

How East Ayrshire decides solar, wind and battery applications

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

All projects in East Ayrshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.