Holmquarry Road (60.4 MW battery storage)

Holmquarry Road is a 60.4 MW battery storage project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 July 2025, not yet built; the record was last updated on 13 October 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60.4 MWbattery storage
approved, not builtstatus in REPD
13 October 2025record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
7 March 2024Application submitted
22 July 2025Section 36 consent granted (Scottish Ministers)
22 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
60.4 MW
Status (REPD)
approved, not built
Record last updated
13 October 2025
Operator or applicant
Big Battery (Holmquarry Road) Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004539
Address (REPD)
Holmquarry Road
Council area (by location)
East Ayrshire
Time to decision
72 weeks
Name in REPD
Holmquarry Road - Battery Storage
REPD reference
11581

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Kilmarnock South Substationbattery storage300operational3.1
Inchbean Farm, Treeswoodhead Roadbattery storage60approved, not built3.3
Kilmarnock Battery Energy Storage Systembattery storage500approved, not built4.9
Camsiscan Farm, Craigiebattery storage350approved, not built5.9
Olympic Business Park, Dundonald - 2 Wind Turbineswind farm8.5refused6.6
Glaxosmithkline Shewalton Roadsolar farm19.9under construction8.0
GlaxoSmithKline Wind Projectwind farm7.5operational8.3
Sneddon Law Community Wind Farmwind farm45under construction8.4
Cowans Lawwind farm49.9refused8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5983, -4.5016).