Energy Projects Near You

Olympic Business Park, Dundonald - 2 Wind Turbines (8.5 MW)

Olympic Business Park, Dundonald - 2 Wind Turbines is an 8.5 MW wind farm project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 16 December 2024; the record was last updated on 20 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.5 MWwind farm
refusedstatus in REPD
20 January 2025record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
30 January 2024Application submitted
16 December 2024Refused by the planning authority

Project details

Technology
wind farm
Capacity
8.5 MW
Status (REPD)
refused
Record last updated
20 January 2025
Operator or applicant
The Farm Energy Partnership
Planning authority
South Ayrshire
Planning application reference
24/00063/APP
Turbines
2
Turbine height
150 m
Address (REPD)
The South & W/O Olympic Business Park, Dundonald, Kilmarnock
Council area (by location)
South Ayrshire
Time to decision
46 weeks
REPD reference
13098

Who decides

ApplicationsSouth AyrshireUK
Decided applications (solar, wind, battery)2010,236
Refused12 (60%)19%
Solar refused0 of 612%
Onshore wind refused12 of 1345%
Battery storage refused0 of 116%
Median time from submission to decision41.7 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Glaxosmithkline Shewalton Roadsolar farm19.9under construction1.6
GlaxoSmithKline Wind Projectwind farm7.5operational2.0
Dunlop Place, Meadowhead Industrial Estatewind turbine7application submitted2.6
Shewalton Landfill Solar Farmsolar farm5under construction3.0
Nethermains Solar Farmsolar farm7.5under construction5.0
Wee Minnemoer, Millport Solar Farm & Battery Storagesolar farm19approved, not built5.0
Holmquarry Roadbattery storage60.4approved, not built6.6
Inchbean Farm, Treeswoodhead Roadbattery storage60approved, not built8.1
Kilmarnock South Substationbattery storage300operational8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5898, -4.6053).