Energy Projects Near You

Wee Minnemoer, Millport Solar Farm & Battery Storage (19 MW)

Wee Minnemoer, Millport Solar Farm & Battery Storage is a 19 MW solar farm project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 February 2024, not yet built; the record was last updated on 19 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19 MWsolar farm
approved, not builtstatus in REPD
19 February 2024record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
17 February 2023Application submitted
9 June 2023Refused by the planning authority
23 August 2023Appeal lodged
9 February 2024Planning permission granted
9 February 2024Appeal allowed
9 February 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
19 MW
Status (REPD)
approved, not built
Record last updated
19 February 2024
Operator or applicant
Comsol Energy
Planning authority
North Ayrshire
Planning application reference
23/00114/PP
Appeal reference
23/00001/REFUSE
Site area
15.3 ha
Address (REPD)
Ne/O Wee Minnemoer, Millport
Council area (by location)
North Ayrshire
Time to decision
51 weeks
Name in REPD
Wee Minnemoer, Millport - Solar Farm & Battery Storage
REPD reference
13090

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nethermains Solar Farmsolar farm7.5under construction<0.1
Shewalton Landfill Solar Farmsolar farm5under construction2.3
GlaxoSmithKline Wind Projectwind farm7.5operational3.1
Glaxosmithkline Shewalton Roadsolar farm19.9under construction3.4
Dunlop Place, Meadowhead Industrial Estatewind turbine7application submitted3.5
Ardeer Peninsula, Ardeerwind farm9.6approved, not built4.6
Olympic Business Park, Dundonald - 2 Wind Turbineswind farm8.5refused5.0
Kilwinning Battery Storagebattery storage100approved, not built5.5
Ardeerwind farm22application withdrawn5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6132, -4.6742).