GlaxoSmithKline Wind Project (7.5 MW)

GlaxoSmithKline Wind Project is a 7.5 MW wind farm project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 June 2013; the record was last updated on 3 October 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
operationalstatus in REPD
3 October 2013record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
6 January 2010Application submitted
1 May 2012Planning permission granted
30 June 2013Operational

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
3 October 2013
Operator or applicant
Glaxosmithkline
Planning authority
North Ayrshire
Planning application reference
09/00878/PP
Turbines
3
Address (REPD)
Shewalton Road Riverside Business Park Irvine Ayrshire
Council area (by location)
North Ayrshire
Time to decision
121 weeks
REPD reference
3841

Who decides

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Glaxosmithkline Shewalton Roadsolar farm19.9under construction0.4
Shewalton Landfill Solar Farmsolar farm5under construction1.0
Dunlop Place, Meadowhead Industrial Estatewind turbine7application submitted1.5
Olympic Business Park, Dundonald - 2 Wind Turbineswind farm8.5refused2.0
Wee Minnemoer, Millport Solar Farm & Battery Storagesolar farm19approved, not built3.1
Nethermains Solar Farmsolar farm7.5under construction3.1
Ardeer Peninsula, Ardeerwind farm9.6approved, not built7.7
Kilwinning Battery Storagebattery storage100approved, not built7.8
Ardoch Farmbattery storage20approved, not built8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5979, -4.6339).