Energy Projects Near You

Ardoch Farm (20 MW battery storage)

Ardoch Farm is a 20 MW battery storage project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 March 2025, not yet built; the record was last updated on 1 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
approved, not builtstatus in REPD
1 April 2025record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
9 January 2025Application submitted
19 March 2025Planning permission granted
19 March 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
1 April 2025
Operator or applicant
Capbal
Planning authority
North Ayrshire
Planning application reference
24/00941/PPM
Address (REPD)
Ardoch Farm, Kilwinning, Ayrshire
Council area (by location)
North Ayrshire
Time to decision
10 weeks
REPD reference
17926

Earlier applications for this site

ApplicationMWSubmittedOutcome
Ardoch Farm 18/00445/PPP2017 May 2018replaced by a revised application

Who decides

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kilwinning Battery Storagebattery storage100approved, not built0.3
Flemyland Battery Storagebattery storage100approved, not built1.0
North West Of Jameston Farmbattery storage19.9approved, not built3.0
Castlehill Solar Farmsolar farm5abandoned3.0
Benthead Farm Solar Farm & Battery Storagesolar farm63approved, not built3.0
Site To North East Of, Lochcraigs Farmsolar farm5operational3.8
Auld Claywind farm9.2refused4.1
Ardeerwind farm22application withdrawn4.2
Ardeer Peninsula, Ardeerwind farm9.6approved, not built4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6646, -4.6843).