Energy Projects Near You

Benthead Farm Solar Farm & Battery Storage (63 MW)

Benthead Farm Solar Farm & Battery Storage is a 63 MW solar farm project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 August 2023, not yet built; the record was last updated on 3 February 2022. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

63 MWsolar farm
approved, not builtstatus in REPD
3 February 2022record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
12 December 2022Application submitted
11 August 2023Section 36 consent granted (Scottish Ministers)
11 August 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
63 MW
Status (REPD)
approved, not built
Record last updated
3 February 2022
Operator or applicant
Locogen Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004702
Address (REPD)
Benhead Farm, Kilwinning
Council area (by location)
North Ayrshire
Time to decision
35 weeks
Contracts for Difference
AR6
Name in REPD
Benthead Farm - Solar Farm & Battery Storage
REPD reference
10541

The scheme also includes 31.1 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
North West Of Jameston Farmbattery storage19.9approved, not built1.7
Flemyland Battery Storagebattery storage100approved, not built2.1
Ardoch Farmbattery storage20approved, not built3.0
Kilwinning Battery Storagebattery storage100approved, not built3.1
Toftsbattery storage19.9approved, not built4.9
Castlehill Solar Farmsolar farm5abandoned5.9
Auld Claywind farm9.2refused6.0
Site To North East Of, Lochcraigs Farmsolar farm5operational6.6
Hunterstonbattery storage5abandoned6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.683, -4.6485).