North West Of Jameston Farm (19.9 MW battery storage)
North West Of Jameston Farm is a 19.9 MW battery storage project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 September 2021, not yet built; the record was last updated on 27 September 2021.
19.9 MWbattery storage
approved, not builtstatus in REPD
27 September 2021record last updated
North Ayrshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 29 October 2018 | Application submitted |
| 21 September 2021 | Planning permission granted |
Project details
- Technology
- battery storage (stand-alone storage)
- Capacity
- 19.9 MW
- Status (REPD)
- approved, not built
- Record last updated
- 27 September 2021
- Operator or applicant
- Private Developer
- Planning authority
- North Ayrshire
- Planning application reference
- 21/00689/MSC
- Address (REPD)
- North West Of Jameston Farm, Dalry, Strathclyde
- Council area (by location)
- North Ayrshire
- Time to decision
- 151 weeks
- REPD reference
- 7133
Who decides
| Applications | North Ayrshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 12 (26%) | 19% |
| Solar refused | 1 of 18 | 12% |
| Onshore wind refused | 10 of 21 | 45% |
| Battery storage refused | 1 of 8 | 16% |
| Median time from submission to decision | 24.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Benthead Farm Solar Farm & Battery Storage | solar farm | 63 | approved, not built | 1.7 |
| Flemyland Battery Storage | battery storage | 100 | approved, not built | 2.3 |
| Ardoch Farm | battery storage | 20 | approved, not built | 3.0 |
| Kilwinning Battery Storage | battery storage | 100 | approved, not built | 3.2 |
| Tofts | battery storage | 19.9 | approved, not built | 3.3 |
| Auld Clay | wind farm | 9.2 | refused | 4.7 |
| Castlehill Solar Farm | solar farm | 5 | abandoned | 5.4 |
| Site To North East Of, Lochcraigs Farm | solar farm | 5 | operational | 5.8 |
| Hunterston | battery storage | 5 | abandoned | 5.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6905, -4.6712).