Flemyland Battery Storage (100 MW)

Flemyland Battery Storage is a 100 MW battery storage project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 December 2024, not yet built; the record was last updated on 13 December 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
13 December 2024record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
20 November 2023Application submitted
6 December 2024Section 36 consent granted (Scottish Ministers)
6 December 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
13 December 2024
Operator or applicant
Flemyland Battery Storage Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004984
Address (REPD)
South East Of Goldcraigs Roads Depot Kilwinning
Council area (by location)
North Ayrshire
Time to decision
55 weeks
REPD reference
13770

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ardoch Farmbattery storage20approved, not built1.0
Kilwinning Battery Storagebattery storage100approved, not built1.0
Benthead Farm Solar Farm & Battery Storagesolar farm63approved, not built2.1
North West Of Jameston Farmbattery storage19.9approved, not built2.3
Castlehill Solar Farmsolar farm5abandoned4.0
Site To North East Of, Lochcraigs Farmsolar farm5operational4.7
Auld Claywind farm9.2refused4.8
Toftsbattery storage19.9approved, not built5.1
Ardeerwind farm22application withdrawn5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6695, -4.6708).