Dunlop Place, Meadowhead Industrial Estate (7 MW wind turbine)
Dunlop Place, Meadowhead Industrial Estate is a 7 MW wind turbine project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 28 July 2025, no decision recorded; the record was last updated on 5 September 2025.
7 MWwind turbine
application submittedstatus in REPD
5 September 2025record last updated
North Ayrshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 28 July 2025 | Application submitted |
Project details
- Technology
- wind turbine
- Capacity
- 7 MW
- Status (REPD)
- application submitted
- Record last updated
- 5 September 2025
- Operator or applicant
- Farm Energy Company
- Planning authority
- North Ayrshire
- Planning application reference
- 25/00334/PP
- Turbines
- 1
- Turbine height
- 200 m
- Address (REPD)
- N/O 1 Dunlop Place, Meadowhead Industrial Estate, Irvine
- Council area (by location)
- North Ayrshire
- Name in REPD
- Dunlop Place, Meadowhead Industrial Estate - Wind turbine
- REPD reference
- 17249
Who decides
| Applications | North Ayrshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 12 (26%) | 19% |
| Solar refused | 1 of 18 | 12% |
| Onshore wind refused | 10 of 21 | 45% |
| Battery storage refused | 1 of 8 | 16% |
| Median time from submission to decision | 24.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Shewalton Landfill Solar Farm | solar farm | 5 | under construction | 1.3 |
| GlaxoSmithKline Wind Project | wind farm | 7.5 | operational | 1.5 |
| Glaxosmithkline Shewalton Road | solar farm | 19.9 | under construction | 1.6 |
| Olympic Business Park, Dundonald - 2 Wind Turbines | wind farm | 8.5 | refused | 2.6 |
| Wee Minnemoer, Millport Solar Farm & Battery Storage | solar farm | 19 | approved, not built | 3.5 |
| Nethermains Solar Farm | solar farm | 7.5 | under construction | 3.5 |
| Ardeer Peninsula, Ardeer | wind farm | 9.6 | approved, not built | 7.8 |
| Kilwinning Battery Storage | battery storage | 100 | approved, not built | 8.8 |
| Ardeer | wind farm | 22 | application withdrawn | 8.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5863, -4.6461).