Shewalton Landfill Solar Farm (5 MW)

Shewalton Landfill Solar Farm is a 5 MW solar farm project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 6 February 2024; the record was last updated on 13 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
under constructionstatus in REPD
13 February 2024record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
10 May 2023Application submitted
15 June 2023Planning permission granted
6 February 2024Construction started

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
under construction
Record last updated
13 February 2024
Operator or applicant
North Ayrshire Council
Planning authority
North Ayrshire
Planning application reference
23/00318/PP
Site area
18.7 ha
Address (REPD)
Landfill Site Shewalton Road, Riverside Business Park, Irvine
Council area (by location)
North Ayrshire
Time to decision
5 weeks
REPD reference
13250

Who decides

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
GlaxoSmithKline Wind Projectwind farm7.5operational1.0
Dunlop Place, Meadowhead Industrial Estatewind turbine7application submitted1.3
Glaxosmithkline Shewalton Roadsolar farm19.9under construction1.4
Wee Minnemoer, Millport Solar Farm & Battery Storagesolar farm19approved, not built2.3
Nethermains Solar Farmsolar farm7.5under construction2.3
Olympic Business Park, Dundonald - 2 Wind Turbineswind farm8.5refused3.0
Ardeer Peninsula, Ardeerwind farm9.6approved, not built6.8
Kilwinning Battery Storagebattery storage100approved, not built7.5
Ardoch Farmbattery storage20approved, not built7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5979, -4.6505).