Kilmarnock Battery Energy Storage System (500 MW)

Kilmarnock Battery Energy Storage System is a 500 MW battery storage project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 April 2025, not yet built; the record was last updated on 15 June 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

500 MWbattery storage
approved, not builtstatus in REPD
15 June 2026record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
28 September 2023Application submitted
7 April 2025Section 36 consent granted (Scottish Ministers)
7 April 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
500 MW
Status (REPD)
approved, not built
Record last updated
15 June 2026
Operator or applicant
Matrix Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004941
Address (REPD)
250 metres (m) to the north of the existing Kilmarnock South Substation
Council area (by location)
East Ayrshire
Time to decision
80 weeks
REPD reference
15176

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Kilmarnock South Substationbattery storage300operational2.0
Camsiscan Farm, Craigiebattery storage350approved, not built2.0
Inchbean Farm, Treeswoodhead Roadbattery storage60approved, not built2.7
Holmquarry Roadbattery storage60.4approved, not built4.9
Alton Muirhouse Farmwind farm6.8refused on appeal8.1
Cowans Lawwind farm49.9refused8.3
Sneddon Law Community Wind Farmwind farm45under construction8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5721, -4.438).