Camsiscan Farm, Craigie (350 MW battery storage)

Camsiscan Farm, Craigie is a 350 MW battery storage project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 January 2024, not yet built; the record was last updated on 8 February 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

350 MWbattery storage
approved, not builtstatus in REPD
8 February 2024record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
18 November 2022Application submitted
26 January 2024Section 36 consent granted (Scottish Ministers)
26 January 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
350 MW
Status (REPD)
approved, not built
Record last updated
8 February 2024
Operator or applicant
Noriker Power Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004658
Address (REPD)
Camsiscan Farm, Craigie, Kilmarnock South, Kilmarnock
Council area (by location)
South Ayrshire
Time to decision
62 weeks
Name in REPD
Camsiscan Farm, Craigie - Battery Energy Storage System
REPD reference
12820

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Kilmarnock Battery Energy Storage Systembattery storage500approved, not built2.0
Inchbean Farm, Treeswoodhead Roadbattery storage60approved, not built2.7
Kilmarnock South Substationbattery storage300operational2.9
Holmquarry Roadbattery storage60.4approved, not built5.9
Alton Muirhouse Farmwind farm6.8refused on appeal10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5551, -4.4475).