Cowans Law (49.9 MW wind farm)

Cowans Law is a 49.9 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 4 November 2010; the record was last updated on 10 June 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWwind farm
refusedstatus in REPD
10 June 2019record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
16 April 2010Application submitted
4 November 2010Refused by the planning authority

Project details

Technology
wind farm
Capacity
49.9 MW
Status (REPD)
refused
Record last updated
10 June 2019
Operator or applicant
Community Windpower (Community Wind Power)
Planning authority
East Ayrshire
Planning application reference
10/0345/PP
Turbines
20
Address (REPD)
Hemphill Road, Moscow, Galston,
Council area (by location)
East Ayrshire
Time to decision
29 weeks
REPD reference
3476

Earlier applications for this site

ApplicationMWSubmittedOutcome
Cowans Law 08/0645/F49.928 July 2008refused 24 June 2010

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sneddon Law Community Wind Farmwind farm45under construction<0.1
Alton Muirhouse Farmwind farm6.8refused on appeal1.8
Whitelee Windfarm Extension phase 2wind farm109operational4.9
East Kingswellwind farm26refused5.2
Blair Data Centrewind farm13.8refused on appeal6.0
Glenouther Renewable Energy Parkwind farm30refused on appeal7.1
Whitelee Windfarm Extension Phase 1wind farm108operational7.8
Whitelee Windfarm Extension Phase 3wind farm12refused on appeal7.8
Land East Of Shieldhill Farmwind farm18refused on appeal8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6431, -4.3947).