Energy Projects Near You

Neilston (150 MW battery storage)

Neilston is a 150 MW battery storage project in East Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 February 2025, not yet built; the record was last updated on 29 September 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

150 MWbattery storage
approved, not builtstatus in REPD
29 September 2025record last updated
East Renfrewshirecouncil area

Planning timeline

DateStage
21 December 2023Application submitted
4 February 2025Section 36 consent granted (Scottish Ministers)
4 February 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
150 MW
Status (REPD)
approved, not built
Record last updated
29 September 2025
Operator or applicant
Apatura (GPC 1119 Ltd)
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004868
Address (REPD)
400 Metres North East Of Glenview Caplaw Road Neilston
Council area (by location)
East Renfrewshire
Time to decision
59 weeks
Name in REPD
Neilston - Battery Storage
REPD reference
14538

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Neilston Greener Grid Park - Phase 2battery storage750approved, not built1.2
Neilston Wind Farmwind farm9.2operational5.4
Harelaw Renewable Energy Parkwind farm117refused5.7
Middleton Road - Linwood Battery Energy Storage Systembattery storage69abandoned5.7
Well Streetbattery storage49.5approved, not built5.9
Middleton Farm Cottage, Middleton Roadsolar farm40approved, not built6.0
Neilston Greener Grid Parkbattery storage50under construction6.1
Saturland Farm, Salterland Roadbattery storage60.8approved, not built7.3
Parkhouse Roadbattery storage24approved, not built7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8013, -4.4858).