Energy Projects Near You

Caledonian Solar Park (18.4 MW)

Caledonian Solar Park is an 18.4 MW solar farm project in Glasgow City, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 June 2023, not yet built; the record was last updated on 3 November 2021. REPD also records that the planning permission expired on 22 June 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.4 MWsolar farm
approved, not builtmay be out of datestatus in REPD
3 November 2021record last updated
Glasgow Citycouncil area

REPD also records that the planning permission expired on 22 June 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
22 October 2021Application submitted
22 June 2023Planning permission granted
22 June 2026Permission expired

Project details

Technology
solar farm
Capacity
18.4 MW
Status (REPD)
approved, not built
Record last updated
3 November 2021
Operator or applicant
Derwent London Green Energy Limited
Planning authority
Glasgow City
Planning application reference
21/03239/FUL
Site area
44.3 ha
Address (REPD)
Lochfauld Road or Balmore Road
Council area (by location)
Glasgow City
Time to decision
87 weeks
REPD reference
9883

Who decides

ApplicationsGlasgow CityUK
Decided applications (solar, wind, battery)2310,236
Refused0 (0%)19%
Solar refused0 of 1912%
Onshore wind refused0 of 145%
Battery storage refused0 of 316%
Median time from submission to decision13.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitehill Energy Storagebattery storage200approved, not built5.2
Broomloan Roadbattery storage49.9approved, not built6.8
Govan Battery Energy Storage Systembattery storage49.9application submitted7.2
Windyhill Battery Storage Facilitybattery storage200under construction7.3
Whitehall Battery Storagebattery storage560approved, not built8.3
Downiebrae Road, Rutherglenbattery storage150approved, not built8.6
Dalmarnock Roadbattery storage40approved, not built8.7
Seath Road, Rutherglenbattery storage50refused8.7
Braidfield Road, Hardgatebattery storage100application submitted9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9082, -4.2611).