Energy Projects Near You

Whitehall Battery Storage (560 MW)

Whitehall Battery Storage is a 560 MW battery storage project in East Dunbartonshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 July 2025, not yet built; the record was last updated on 29 July 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

560 MWbattery storage
approved, not builtstatus in REPD
29 July 2025record last updated
East Dunbartonshirecouncil area

Planning timeline

DateStage
16 November 2023Application submitted
22 July 2025Section 36 consent granted (Scottish Ministers)
22 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
560 MW
Status (REPD)
approved, not built
Record last updated
29 July 2025
Operator or applicant
Apatura
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004982
Address (REPD)
Cochno Road, East Bearsden
Council area (by location)
East Dunbartonshire
Time to decision
88 weeks
REPD reference
15797

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Windyhill Battery Storage Facilitybattery storage200under construction1.1
Braidfield Road, Hardgatebattery storage100application submitted2.2
Kilpatrick Hillswind farm60application withdrawn4.4
Vale of Leven Wind Farmwind farm70application submitted4.4
Land off Shilton Lanebattery storage19abandoned6.2
Land SW of Shilton Cottagebattery storage29.9operational7.8
Barnwell, Wright Streetbattery storage49.9refused7.9
Caledonian Solar Parksolar farm18.4approved, not built8.3
East Fulwood Greenock Road Solar Farmsolar farm14.3approved, not built8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9359, -4.3852).