Energy Projects Near You

Solar, wind and battery projects near Paisley (PA1)

48 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA1 (Renfrewshire): 8 are waiting for a planning decision, 31 approved but not yet running, 3 operational. The largest live scheme is Neilston Greener Grid Park - Phase 2 (750 MW battery storage, approved on 13 August 2025, not yet built), 5.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48projects within 10 km
8awaiting a decision
31approved, not running
3operational

Projects within 10 km of PA1

Projects of 1 MW and more (29)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Neilston Greener Grid Parkbattery storagebattery storage50under constructionupdated Mar 2026Jan 2021granted Apr 2022Mar 2026Renfrewshire0.6
Well Streetbattery storagebattery storage49.5approved, not builtupdated Mar 2023Feb 2023granted May 2023Mar 2023Renfrewshire1.1
Laigh Park Water Treatment Worksbattery storagebattery storage49.5application submittedupdated Oct 2025Sep 2025—Oct 2025Renfrewshire1.4
Glasgow Airport Solar Farmsolar farmsolar farm19.9under constructionupdated Nov 2023Nov 2022granted Apr 2023Nov 2023Renfrewshire2.2
Barnwell, Wright Streetbattery storagebattery storage49.9refusedupdated Aug 2024Feb 2024refused May 2024Aug 2024Renfrewshire2.5
Middleton Farm Cottage, Middleton Roadsolar farmsolar farm40approved, not builtupdated Sep 2025Mar 2025granted Sep 2025Sep 2025Renfrewshire3.8
Middleton Road, Linwoodsolar farmsolar farm1.6approved, not builtupdated Feb 2025Apr 2024granted Jan 2025Feb 2025Renfrewshire4.3
Middleton Road - Linwood Battery Energy Storage Systembattery storagebattery storage69abandonedupdated May 2025Feb 2023granted May 2024May 2025Renfrewshire4.4
East Fulwood Energy Storagebattery storagebattery storage400application submittedupdated Jun 2026Jan 2026—Jun 2026Renfrewshire4.8
East Fulwood Greenock Road Solar Farmsolar farmsolar farm14.3approved, not built may be out of dateupdated Aug 2025Aug 2022granted Jan 2023Aug 2025Renfrewshire4.8
Saturland Farm, Salterland Roadbattery storagebattery storage60.8approved, not builtupdated Apr 2025Nov 2023granted Dec 2024Apr 2025Glasgow City5.1
Neilston Greener Grid Park - Phase 2battery storagebattery storage750approved, not builtupdated Oct 2025Dec 2024granted Aug 2025Oct 2025Renfrewshire5.5
Parkhouse Roadbattery storagebattery storage24approved, not builtupdated Aug 2025Mar 2024granted Aug 2025Aug 2025Glasgow City5.5
Govan Battery Energy Storage Systembattery storagebattery storage49.9application submittedupdated Mar 2025Feb 2025—Mar 2025Glasgow City6.4
Neilstonbattery storagebattery storage150approved, not builtupdated Sep 2025Dec 2023granted Feb 2025Sep 2025East Renfrewshire6.4
Kennishead Roadbattery storagebattery storage40application withdrawnupdated Mar 2026Jun 2025—Mar 2026Glasgow City6.5
Broomloan Roadbattery storagebattery storage49.9approved, not builtupdated Oct 2024Mar 2024granted Oct 2024Oct 2024Glasgow City6.6
Artfield Forest Wind Farmwind farmwind farm67.2approved, not builtupdated Jul 2022Mar 2021granted Feb 2023Jul 2022Renfrewshire7.2
Braidfield Road, Hardgatebattery storagebattery storage100application submittedupdated Feb 2025Dec 2024—Feb 2025West Dunbartonshire8.3
Land off Shilton Lanebattery storagebattery storage19abandonedupdated Nov 2019Aug 2017—Nov 2019Renfrewshire8.4
Houston Solar PV Farm & Energy Storage Facilitysolar farmsolar farm75approved, not builtupdated Jun 2026Oct 2023granted Mar 2026Jun 2026Renfrewshire8.6
Houston Solar PV Farm & Energy Storage Facilitybattery storagebattery storage25approved, not builtupdated Jun 2026Oct 2023granted Mar 2026Jun 2026Renfrewshire8.6
Land SW of Shilton Cottagebattery storagebattery storage29.9operationalupdated Jun 2026Apr 2018—Jun 2026Renfrewshire8.8
Middleton Wind Farmwind farmwind farm12operationalupdated Mar 2015Feb 2008granted Aug 2011Mar 2015East Renfrewshire9.1
Vale of Leven Wind Farmwind farmwind farm70application submitted may be out of dateupdated Nov 2023Oct 2023—Nov 2023West Dunbartonshire9.1
Vale of Leven Wind Farmbattery storagebattery storage20application submitted may be out of dateupdated Nov 2023Oct 2023—Nov 2023West Dunbartonshire9.1
Locher Works, Kilbarchan Roadsolar farmsolar farm3approved, not builtupdated Sep 2024Mar 2024granted Sep 2024Sep 2024Renfrewshire9.3
Windyhill Battery Storage Facilitybattery storagebattery storage200under constructionupdated Jun 2026Oct 2021granted Jun 2022Jun 2026East Dunbartonshire9.9
Harelaw Renewable Energy Parkwind farmwind farm117refusedupdated Feb 2014May 2009refused Sep 2013Feb 2014East Renfrewshire9.9
Smaller schemes under 1 MW, mostly rooftop solar (19)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cpi Medicines Manufacturing Centre, Netherton Squarerooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Jul 2023granted Jan 2024Mar 2024Renfrewshire0.9
Lightyear Building, Marchburn Drive - Block A - Solar Panelsrooftop solarrooftop solar0.4application submittedupdated Mar 2026Jan 2026—Mar 2026Renfrewshire1.9
Glasgow Airport Solar Farmbattery storagebattery storage—under constructionupdated May 2024Nov 2022granted Apr 2023May 2024Renfrewshire2.2
Middleton Road, Linwoodbattery storagebattery storage—approved, not builtupdated Feb 2025Apr 2024granted Jan 2025Feb 2025Renfrewshire4.3
Decathlon, Old Govan Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Dec 2023granted Mar 2024Apr 2024Renfrewshire4.3
Cartside Avenue, Inchinnanrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Oct 2022granted Feb 2023Mar 2023Renfrewshire4.3
Fifty Pitches Placerooftop solarrooftop solar0.5approved, not builtupdated Dec 2023Aug 2023granted Dec 2023Dec 2023Glasgow City4.5
Bray Controls UK, Fountain Crescentrooftop solarrooftop solar0.2application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024Renfrewshire4.7
Glasgow Museums Resource Centre, Woodhead Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Nov 2024granted Feb 2025Mar 2025Glasgow City5.0
Shipyardrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Glasgow City5.2
Shipyard, Govan Roadrooftop solarrooftop solar0.8approved, not builtupdated Jul 2024Mar 2024granted Jul 2024Jul 2024Glasgow City6.5
Helen Streetrooftop solarrooftop solar0.3approved, not builtupdated Nov 2023Jul 2023granted Oct 2023Nov 2023Glasgow City6.5
Allerdyce Roadrooftop solarrooftop solar0.2application withdrawnupdated Jun 2025Dec 2023—Jun 2025Glasgow City7.1
Glasgow High School, Crow Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Glasgow City7.4
David Lloyd Leisure Health Club, Stewarton Roadrooftop solarrooftop solar0.5approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024East Renfrewshire7.8
Argyle Streetrooftop solarrooftop solar0.6approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025Glasgow City8.2
Kelvin Hall Sports Arena, Argyle Streetrooftop solarrooftop solar0.6approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024Glasgow City8.2
Hutchesons Grammar Schoolrooftop solarrooftop solar0.2operationalupdated May 2023Mar 2020granted Jun 2020May 2023Glasgow City8.5
Old Kilpatrick Service Reservoir, Mount Pleasant Roadsolar farmsolar farm0.4approved, not builtupdated Mar 2023Mar 2023granted Oct 2023Mar 2023West Dunbartonshire9.9

Distance from the average position of the PA1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm70700154
Rooftop solar16212105.3
Wind farm41111137
Battery storage21511111,979

MW in pipeline: pending, approved and under-construction capacity.

How Renfrewshire decides solar, wind and battery applications

ApplicationsRenfrewshireUK
Decided applications (solar, wind, battery)1510,236
Refused4 (27%)19%
Solar refused2 of 1012%
Battery storage refused2 of 516%
Median time from submission to decision21.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

All projects in Renfrewshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PA1, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.