Energy Projects Near You

Houston Solar PV Farm & Energy Storage Facility (75 MW)

Houston Solar PV Farm & Energy Storage Facility is a 75 MW solar farm project in Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 March 2026, not yet built; the record was last updated on 22 June 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

75 MWsolar farm
approved, not builtstatus in REPD
22 June 2026record last updated
Renfrewshirecouncil area

Planning timeline

DateStage
4 October 2023Application submitted
20 March 2026Section 36 consent granted (Scottish Ministers)
20 March 2031Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
75 MW
Status (REPD)
approved, not built
Record last updated
22 June 2026
Operator or applicant
The Old Rectory
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004825
Site area
129.0 ha
Address (REPD)
Houston Village Hall, 19 Main Street, Houston, Johnstone
Council area (by location)
Renfrewshire
Time to decision
128 weeks
REPD reference
14293

The scheme also includes 25 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Artfield Forest Wind Farmwind farm67.2approved, not built3.9
Middleton Road - Linwood Battery Energy Storage Systembattery storage69abandoned4.2
Middleton Farm Cottage, Middleton Roadsolar farm40approved, not built4.8
East Fulwood Greenock Road Solar Farmsolar farm14.3approved, not built5.2
East Fulwood Energy Storagebattery storage400application submitted5.2
Land SW of Shilton Cottagebattery storage29.9operational5.6
Land off Shilton Lanebattery storage19abandoned6.8
Well Streetbattery storage49.5approved, not built7.5
Glasgow Airport Solar Farmsolar farm19.9under construction7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8676, -4.5502).