Energy Projects Near You

High Boydstone Farm (100 MW battery storage)

High Boydstone Farm is a 100 MW battery storage project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 June 2025, not yet built; the record was last updated on 1 July 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
1 July 2025record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
11 October 2024Application submitted
2 June 2025Section 36 consent granted (Scottish Ministers)
2 June 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
1 July 2025
Operator or applicant
New Energy Partnership
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005094
Address (REPD)
North West Of High Boydstone Farm
Council area (by location)
North Ayrshire
Time to decision
33 weeks
Name in REPD
High Boydstone Farm - Battery Energy Storage Facility
REPD reference
16174

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Ardrossanwind farm24operational1.5
Ardrossan Extensionwind farm6operational1.5
Sorbie Farmwind farm9under construction2.2
Sorbie Farm wind clusterwind farm7.5application withdrawn2.2
Meiklelaught Farmbattery storage30approved, not built3.6
Site To North East Of, Lochcraigs Farmsolar farm5operational4.9
Ardeerwind farm22application withdrawn5.0
Blackshaw Community Wind Farmwind farm21refused on appeal5.4
Auld Claywind farm9.2refused5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6545, -4.8212).