Energy Projects Near You

Hunterston Test Centre (Phase 2) (8 MW wind turbine)

Hunterston Test Centre (Phase 2) is an 8 MW wind turbine project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 4 August 2016; the record was last updated on 1 September 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWwind turbine
application withdrawnstatus in REPD
1 September 2016record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
28 January 2016Application submitted
4 August 2016Application withdrawn

Project details

Technology
wind turbine
Capacity
8 MW
Status (REPD)
application withdrawn
Record last updated
1 September 2016
Operator or applicant
Scottish Enterprise/SSE
Planning authority
North Ayrshire
Planning application reference
16/00060/PP
Turbines
1
Turbine height
220 m
Address (REPD)
Hunterston Construction Yard, Fairlie Largs, Largs
Council area (by location)
North Ayrshire
REPD reference
6080

Who decides

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hunterston Test Centrewind farm13decommissioned0.3
Crosbie Wind Farmwind farm98application submitted1.7
Crosbie Wind Farmbattery storage50application submitted1.7
Hunterston Grid Services Complex Energy Storage Facilitybattery storage400approved, not built1.8
Land at Hunterston Estatesolar farm5abandoned2.2
Hunterstonewind farm30refused3.2
Blackshaw Community Wind Farmwind farm21refused on appeal5.1
Kelburnwind farm28operational5.5
Wardlaw Woodwind farm18operational6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.734, -4.8842).