Hunterston Grid Services Complex Energy Storage Facility (400 MW)

Hunterston Grid Services Complex Energy Storage Facility is a 400 MW battery storage project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 January 2022, not yet built; the record was last updated on 3 February 2022. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtstatus in REPD
3 February 2022record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
11 August 2021Application submitted
5 January 2022Section 36 consent granted (Scottish Ministers)
5 January 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
3 February 2022
Operator or applicant
Amp Energy
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003319
Address (REPD)
Campbelton Farm, Campbelton Road, West Kilbride
Council area (by location)
North Ayrshire
Time to decision
21 weeks
Name in REPD
Hunterston Grid Services Complex - Energy Storage Facility
REPD reference
10535

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Hunterston Estatesolar farm5abandoned0.4
Hunterston Test Centre (Phase 2)wind turbine8application withdrawn1.8
Hunterston Test Centrewind farm13decommissioned2.1
Crosbie Wind Farmwind farm98application submitted2.2
Crosbie Wind Farmbattery storage50application submitted2.3
Blackshaw Community Wind Farmwind farm21refused on appeal3.8
Hunterstonewind farm30refused4.6
Wardlaw Woodwind farm18operational5.6
Kelburnwind farm28operational6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7184, -4.8782).