Largie Windfarm II (21 MW)

Largie Windfarm II is a 21 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 8 March 2007; the record was last updated on 6 April 2007.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWwind farm
refusedstatus in REPD
6 April 2007record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
12 August 2004Application submitted
8 March 2007Refused by the planning authority

Project details

Technology
wind farm
Capacity
21 MW
Status (REPD)
refused
Record last updated
6 April 2007
Operator or applicant
Ecogen and Eurus Energy UK
Planning authority
Argyll and Bute
Planning application reference
04/01606/DET
Turbines
19
Address (REPD)
Largie, Central Kintyre Ridge, Near Tayinloan
Council area (by location)
Argyll and Bute
Time to decision
134 weeks
REPD reference
3217

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Narachan Wind Farmwind farm72.6refused3.4
Corriechreivewind farm30refused3.5
Killean Wind Farmwind farm59.4application submitted5.2
High Constellation Wind Farmwind farm48approved, not built7.2
Cour Wind Farmwind farm20.5operational7.4
Deucheran Hillwind farm15.8operational8.0
Clachaig Glenwind farm60approved, not built8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6942, -5.6004).