Energy Projects Near You

High Constellation Wind Farm (48 MW)

High Constellation Wind Farm is a 48 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 June 2020, not yet built; the record was last updated on 16 July 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. REPD records the planning permission as expiring on 26 June 2026, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48 MWwind farm
approved, not builtmay be out of datestatus in REPD
16 July 2024record last updated
Argyll and Butecouncil area

REPD records the planning permission as expiring on 26 June 2026, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
28 May 2019Application submitted
26 June 2020Section 36 consent granted (Scottish Ministers)
26 June 2026Permission expired

Project details

Technology
wind farm
Capacity
48 MW
Status (REPD)
approved, not built
Record last updated
16 July 2024
Operator or applicant
BayWa r.e. UK Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00001857
Turbines
10
Turbine height
150 m
Address (REPD)
Mull of Kintyre
Council area (by location)
Argyll and Bute
Time to decision
56 weeks
Contracts for Difference
AR4
REPD reference
7345

The scheme also includes 55.5 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Cour Wind Farmwind farm20.5operational2.5
Eascairt Wind Farmwind farm26approved, not built4.7
Narachan Wind Farmwind farm72.6refused6.5
Sheirdrim Renewable Energy Development Solarsolar farm20refused on appeal6.7
Sheirdrim Renewable Energy Development Windwind farm114refused on appeal6.7
Sheirdrim Renewable Energy Development Batterybattery storage38refused on appeal6.7
Largie Windfarm IIwind farm21refused7.2
Corriechreivewind farm30refused7.3
Gartnagrenachwind farm24application withdrawn8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7028, -5.487).