Freasdail Wind Farm (22.5 MW)

Freasdail Wind Farm is a 22.5 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 8 February 2017; the record was last updated on 31 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22.5 MWwind farm
operationalstatus in REPD
31 May 2017record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
25 October 2012Application submitted
25 September 2013Refused by the planning authority
15 April 2014Planning permission granted
15 April 2014Appeal allowed
20 February 2016Construction started
8 February 2017Operational

Project details

Technology
wind farm
Capacity
22.5 MW
Status (REPD)
operational
Record last updated
31 May 2017
Operator or applicant
The Renewables Infrastructure Group (TRIG)
Planning authority
Argyll and Bute
Planning application reference
12/02150/PP
Appeal reference
13/00022/REFPLA
Turbines
11
Address (REPD)
Land East Of Loch Freasdail And North Of Loch Cruinn Whitehouse By Tarbert Argyll And Bute
Council area (by location)
Argyll and Bute
Time to decision
77 weeks
REPD reference
3886

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sheirdrim Renewable Energy Development Solarsolar farm20refused on appeal1.8
Sheirdrim Renewable Energy Development Batterybattery storage38refused on appeal1.8
Sheirdrim Renewable Energy Development Windwind farm114refused on appeal1.8
Gartnagrenachwind farm24application withdrawn2.0
Eascairt Wind Farmwind farm26approved, not built4.3
Earraghail Renewable Energy Developmentwind farm78application submitted7.3
Earraghail Renewable Energy Developmentsolar farm5refused7.5
High Constellation Wind Farmwind farm48approved, not built8.3
Corriechreivewind farm30refused9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.777, -5.4706).