Energy Projects Near You

Earraghail Renewable Energy Development (78 MW wind farm)

Earraghail Renewable Energy Development is a 78 MW wind farm project in Argyll and Bute, Scotland. Its status: refused on 14 February 2025 (Scottish Government Energy Consents Unit). The Renewable Energy Planning Database (July 2026 extract) still records: application submitted on 21 February 2022, no decision recorded; the record was last updated on 8 March 2023. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

78 MWwind farm
refusedstatus (Scottish Government Energy Consents Unit; status in REPD: application submitted)
8 March 2023record last updated
Scotlandcouncil area

Planning timeline

DateStage
21 February 2022Application submitted
14 February 2025Refused (Scottish Ministers)

Status source: Scottish Government Energy Consents Unit. The Renewable Energy Planning Database (July 2026 extract) still shows this project as “application submitted”.

Project details

Technology
wind farm
Capacity
78 MW
Status
refused (Scottish Government Energy Consents Unit; REPD: application submitted)
Record last updated
8 March 2023
Operator or applicant
ScottishPower Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003421
Turbines
13
Turbine height
180 m
Address (REPD)
Land approximately 1.2km south of Tarbert and 1.1km north of Skipness,
Council area (by location)
not known
REPD reference
7873

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Earraghail Renewable Energy Developmentsolar farm5refused1.2
Freasdail Wind Farmwind farm22.5operational7.3
Sheirdrim Renewable Energy Development Windwind farm114refused on appeal8.9
Sheirdrim Renewable Energy Development Batterybattery storage38refused on appeal8.9
Sheirdrim Renewable Energy Development Solarsolar farm20refused on appeal8.9
Gartnagrenachwind farm24application withdrawn9.0
Eascairt Wind Farmwind farm26approved, not built9.6

Status and events credited to a named source are from that source; other dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8163, -5.3778).