Airigh Wind Farm (58.8 MW)

Airigh Wind Farm is a 58.8 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 20 May 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

58.8 MWwind farm
abandonedstatus in REPD
20 May 2024record last updated
Scotlandcouncil area

Planning timeline

DateStage
1 September 2017Application submitted
20 March 2020Section 36 consent granted (Scottish Ministers)
20 March 2025Permission expired

Project details

Technology
wind farm
Capacity
58.8 MW
Status (REPD)
abandoned
Record last updated
20 May 2024
Operator or applicant
EDF Energy Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00000471
Turbines
14
Turbine height
150 m
Address (REPD)
Airigh Wind Farm SW of, Tarbert
Council area (by location)
not known
Time to decision
133 weeks
REPD reference
6464

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Gartnagrenachwind farm24application withdrawn8.7
Freasdail Wind Farmwind farm22.5operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8423, -5.5766).