Alt Dearg (42 MW wind farm)

Alt Dearg is a 42 MW wind farm project in Argyll and Bute, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 14 November 2007; the record was last updated on 4 January 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42 MWwind farm
refusedstatus in REPD
4 January 2010record last updated
Argyll and Butecouncil area

Planning timeline

DateStage
1 June 2006Application submitted
14 November 2007Refused by the planning authority

Project details

Technology
wind farm
Capacity
42 MW
Status (REPD)
refused
Record last updated
4 January 2010
Operator or applicant
Npower Renewables
Planning authority
Argyll and Bute
Planning application reference
06/01158/DET
Turbines
15
Address (REPD)
Alt Dearg Wind Farm By Stronachullin Farm Ardrishaig
Council area (by location)
Argyll and Bute
Time to decision
76 weeks
REPD reference
3545

Who decides

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Srondoire Community Wind Farmwind farm6operational1.5
Allt Dearg Wind Farmers LLPwind farm10.8operational1.5
Allt Rubha Wind Farmwind farm27application withdrawn4.1
High Brenfield Wind Farmwind farm66application submitted5.2
Cruach Brenfield Wind Farmwind farm59.4application withdrawn5.8
Shira Wind Farmwind farm79application withdrawn8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9465, -5.4727).