Energy Projects Near You

Solar, wind and battery projects near Bowmore (PA43)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA43 (Argyll and Bute): 1 approved but not yet running. The largest live scheme is Glenegedale Lotts, Turbine Lotts (0.2 MW solar farm, approved on 20 June 2024, not yet built), 8.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of PA43

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Laggan Windclusterwind farmwind farm3refusedupdated Oct 2011May 1995refused Jun 1999Oct 2011Argyll and Bute2.8
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Glenegedale Lotts, Turbine Lottssolar farmsolar farm0.2approved, not builtupdated Jul 2024Feb 2024granted Jun 2024Jul 2024Argyll and Bute8.3

Distance from the average position of the PA43 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.2
Wind farm100010

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.