Energy Projects Near You

Solar, wind and battery projects near Port Charlotte (PA48)

1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of PA48 (Argyll and Bute): none of them is pending, approved or operational. The largest scheme is Laggan Windcluster (3 MW wind farm, refused on 11 June 1999), 7.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1projects within 10 km
0awaiting a decision
0approved, not running
0operational

Projects within 10 km of PA48

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Laggan Windclusterwind farmwind farm3refusedupdated Oct 2011May 1995refused Jun 1999Oct 2011Argyll and Bute7.8

Distance from the average position of the PA48 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm100010

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.