Energy Projects Near You

Solar, wind and battery projects near Crossapol (PA77)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA77 (Argyll and Bute): 1 approved but not yet running. The largest live scheme is Ionad Iomairt Thiriodh, Crossapol (0.1 MW solar farm, approved on 17 December 2025, not yet built), 0.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of PA77

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hillcrest Farmwind farmwind farm1.7application withdrawnupdated Jun 2011Jul 2009refused Oct 2012Jun 2011Argyll and Bute2.9
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ionad Iomairt Thiriodh, Crossapolsolar farmsolar farm0.1approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Argyll and Bute0.3

Distance from the average position of the PA77 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.1
Wind farm100000

MW in pipeline: pending, approved and under-construction capacity.

How Argyll and Bute decides solar, wind and battery applications

ApplicationsArgyll and ButeUK
Decided applications (solar, wind, battery)4910,236
Refused22 (45%)19%
Solar refused0 of 412%
Onshore wind refused21 of 4145%
Battery storage refused1 of 416%
Median time from submission to decision53.3 weeks17.0 weeks
Appeals lodged / allowed5 / 4—

All projects in Argyll and Bute

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.